ACTIVIDAD DESACTUALIZADA 2010 Unidad Basico K Ferr. K Manu. K Petr. Porcentaje Mano Obra
RED DE BAJA TENSIÓN





RED B.T. 2(7 x 500 MCM) ML 1604363,29 28,28

1,61
RED B.T. 2(7 x 400 MCM) ML 1425415,29 22,68

1,81
RED B.T. 2(7 x 300 MCM) ML 1080539,29 16,94

2,38
RED B.T. 2(7 x 4/0 AWG) ML 155475,29 11,48

16,56
RED B.T. 11 x 300 MCM ML 849149,59 13,31

2,4
RED B.T. 7 x 400 MCM ML 712708,61 11,34

1,81
RED B.T. 7 x 4/0 AWG ML 77738,61 5,74

16,56
RED B.T. 3 x 350 + 1 x 250 MCM ML 333634,22 5,27

2,25
RED B.T. 3 x 400 + 1 x 300 MCM ML 382781,22 6,07

1,96
RED B.T. 3 x 4/0 + 1 x 2/0 AWG ML 41283,22 3

18,19
RED B.T. 3 x 2/0 + 1 x 1/0 AWG ML 30331,22 2,05

24,76
RED B.T. 3 x 1/0 + 1 x 2 AWG ML 25416,22 1,56

29,55
RED B.T. 3 x 2 + 1 x 4 AWG ML 19293,22 ,98

38,93
BARRAJE PREM. 6 SALIDAS UN 200170,98 2,52

6,1
BORNA 4/0 UN 46696,18 ,16

10,79